s Updates Archive - Page 14 of 14 - National Grid: Nassau

Updates

Here you’ll find the latest information regarding the Northwest Nassau Natural Gas Integrity Project. Make sure to use the Contact Us page and sign up to get these updates directly to your email inbox.

Last week our construction team continued installing components for the Old Westbury regulator station and installed the precast vaults for the Roslyn Heights regulator station. The team also began gas main installation on Hewlett Avenue in East Williston. Our outreach…

Read More

Last week our construction team continued installing components for the Old Westbury regulator station and began excavation for the Roslyn Heights regulator station. The team also began preparation for gas main installation on Hewlett Avenue in East Williston. Our outreach…

Read More

Over the last week our construction team has continued installing components for the Old Westbury regulator stations. This week we will continue our work there, and resume work on Coolidge Street. We will also begin trenching and gas main installation…

Read More

Over the last week our construction team has been installing components for the Old Westbury regulator stations. This week we will continue to focus our efforts there, with no work planned on Coolidge Street. We will also begin activities for…

Read More

Over the last week our construction team prepared for, and resumed, work on the Old Westbury regulator stations, with activities occurring both on and offsite. This week we will be focusing our efforts there, with no work planned on Coolidge…

Read More

Over the past week, our construction team has completed installation of the new gas main and temporary repaving along Harding Avenue, with work in the intersection of Harding Avenue and Coolidge Street slated for early this week. The outreach team continues…

Read More

This past week, our construction team has been hard at work on Harding Avenue installing the new gas main and completing temporary repaving of the street as quickly as possible. This work is ongoing, and will turn onto Coolidge Street…

Read More

This past week, our construction team continued preparation off and on site for upcoming work in Roslyn Heights. They were in the field early this week, completing sawcutting along Harding Avenue and Coolidge Street, and backfilled the precast vaults on…

Read More

Over the last week, our construction crew was mainly working offsite to prefabricate the materials for the regulator stations. We will be back onsite this week working only during the day, generally from 7:00 am to 3:30 pm. *Over the next…

Read More

Over the last two months, our community engagement team has been knocking on doors to speak with residents about the work we have been doing along Old Westbury Road and Powerhouse Road, as well as upcoming work in Roslyn Heights…

Read More

Welcome to National Grid’s Northwest Nassau Natural Gas Reliability Project website! Here you’ll find information about the project including periodic updates, our project map, and the answers to frequently asked questions. You can also sign up for our email newsletter…

Read More

Enter your email below to receive the most recent construction updates direct to your inbox! You can also call or email your local project team with any questions, concerns, or suggestions.