Last week our construction team continued working on the tie-in on Coolidge Avenue and Powerhouse Road and continued backfilling the regulator stations in Roslyn Heights. Our team also continued work on Roslyn Road south of I.U. Willets Road, and began…
Last week our construction team began working on the tie-in on Coolidge Street and Powerhouse Road and continued backfilling the regulator stations in Roslyn Heights. Our team also continued work on Roslyn Road south of I.U. Willets Road. The outreach…
Last week our construction team continued working on the tie-in on Jefferson Avenue and backfilling the regulator stations in Roslyn Heights. We began test pitting on Roslyn Road south of I.U. Willets Road in advance of upcoming gas main installation….
Last week our construction team began working on the tie-in on Jefferson Avenue and continued backfilling the regulator stations in Roslyn Heights. The outreach team will continue to keep residents informed during work and give notice of upcoming activities. *Over…
Last week our construction team continued backfilling the regulator stations in Roslyn Heights and did work for the tie-in on the regulator stations in Old Westbury. The outreach team will continue to keep residents informed during work and give notice…
Last week our construction team continued backfilling for the regulator stations in Roslyn Heights. The outreach team will continue to keep residents informed during work and give notice of upcoming activities. *Over the next week, neighbors can expect to see:…
Last week our construction team continued backfilling and installing control lines for the regulator stations in Roslyn Heights. The outreach team will continue to keep residents informed during work and give notice of upcoming activities. *Over the next week, neighbors…
Last week our construction team continued backfilling and installing control lines for the regulator stations in Roslyn Heights. The outreach team will continue to keep residents informed during work and give notice of upcoming activities. *Over the next week, neighbors…
Last week our construction team continued backfilling and installing control lines for the regulator stations in Roslyn Heights. The outreach team will continue to keep residents informed during work and give notice of upcoming activities. *Over the next week, neighbors…
Last week our construction team continued backfilling and installing control lines for the regulator stations in Roslyn Heights. The outreach team will continue to keep residents informed during work and give notice of upcoming activities. *Over the next week, neighbors can…
Last week our construction team continued backfilling and installing control lines for the regulator stations in Roslyn Heights and continued tie-in work for the regulator stations off of Red Ground Road and the westbound LIE service road. The outreach team…
Last week our construction team continued installing regulator station gas piping in Roslyn Heights and continued tie-in work for the regulator stations off of Red Ground Road and the westbound LIE service road. The outreach team will continue to keep…