We are approaching the end of regulator station installation, which means our next step will be preparing to restore curbing on Harding Avenue and Coolidge Avenue. Once this work is complete, contractors will focus their efforts on full road restoration.

The opening day of school is approaching, and as requested we have proactively coordinated with the schools and bus transportation company to confirm a temporary, alternative school bus stop. Due to the meticulous nature of curb replacement and upcoming paving work, school bus traffic will be temporarily re-routed to a temporary bus stop.

The temporary stop will be located at the corner of Harding Avenue and Jefferson Avenue. This temporary bus stop will be in place from Tuesday, September 3 until the paving process is complete.

We look forward to bringing you more information regarding the upcoming milling and paving of Harding Avenue and Coolidge Avenue in the coming days.

*Over the next week, neighbors can expect to see:

Traffic management updates:

  • During the day, there will be changes in traffic patterns on Coolidge Avenue with flaggers present to redirect traffic as necessary.

As always, feel free to reach out by emailing us at NWNassau@NationalGridGasProjectsNY.com, or by calling our project outreach team at (516) 882-4864. You can also use the Contact Us page of our website to submit any questions, comments, or concerns.

*Please note, due to the complexities of outdoor construction, schedule is subject to change.