Last week our construction team continued trenching on Roslyn Road between Locust Lane and Club Drive. The outreach team will continue to keep residents informed during work and give notice of upcoming activities, maintaining social distancing and eliminating any close contact.

*Over the next week, neighbors can expect to see:

  • Continued gas main installation on Roslyn Road between Locust Lane and Club Drive.

Traffic Management Updates:

  • The right turn lane from Roslyn Road onto Locust Lane will be closed.
  • The two northbound lanes on Roslyn Road will be closed during working hours. Traffic will be kept to the two southbound lanes allowing for one lane of traffic in either direction.
  • The intersection of Roslyn Road and Club Drive will be closed.
  • Our crews will have flaggers present to redirect traffic as necessary.

Please feel free to reach out by emailing us at NWNassau@NationalGridGasProjectsNY.com, or by calling our project outreach team at (516) 882-4864. You can also use the Contact Us page of our website to submit any questions, comments, or concerns.

For more information about National Grid’s response to COVID-19, please visit: ngrid.com/covid-19

*Please note, due to the complexities of outdoor construction, schedule is subject to change.