We are pleased to note that last week our construction team completed gas main installation on Locust Lane between Corn Crib Lane and Oak Lane. Our team also continued gas main installation on Locust Lane between Corn Crib Lane and Roslyn Road. As always, our outreach team continues to keep residents informed during work and give notice of upcoming activities.
*Over the next week, neighbors can expect to see:
- Backfilling on Locust Lane between Corn Crib Lane and Oak Lane.
- Gas main installation on Locust Lane between Oak Lane and Roslyn Road.
- During the day there will be changes in traffic patterns on Locust Lane with flaggers present to redirect traffic as necessary.
Please feel free to reach out by emailing us at NWNassau@NationalGridGasProjectsNY.com, or by calling our project outreach team at (516) 882-4864. You can also use the Contact Us page of our website to submit any questions, comments, or concerns.
*Please note, due to the complexities of outdoor construction, schedule is subject to change.