Over the last week, our construction team continued trenching, backfilling and pipe installation on Roslyn Road. The outreach team will continue to keep residents informed during work and give notice of upcoming activities, maintaining social distancing and eliminating any close contact.
*Over the next week, neighbors can expect to see:
- Gas backfilling on Roslyn Road between Barnyard Lane and Hewlett Drive.
- Trenching and gas main installation on Roslyn Road between Post Avenue and East Williston Avenue
Traffic Management Updates:
- Roslyn Road will be closed to all through traffic during the working hours from I.U. Willets Road to East Williston Avenue. Our crews will work diligently to accommodate residents with driveways on Roslyn Road.
- Roslyn Road will be closed to commercial traffic at all times from I.U. Willets Road to East Williston Avenue.
- The right turn lane from Roslyn Road onto Locust Lane will remain closed.
- Our crews will have flaggers present to redirect traffic as necessary.
As always, feel free to reach out by emailing us at NWNassau@NationalGridGasProjectsNY.com, or by calling our project outreach team at (516) 882-4864. You can also use the Contact Us page of our website to submit any questions, comments, or concerns.
For more information about National Grid’s response to COVID-19, please visit: ngrid.com/covid-19
*Please note, due to the complexities of outdoor construction, schedule is subject to change.