Over the last week, our construction team continued trenching and gas main installation on Roslyn Road between East Williston Avenue and Jericho Turnpike and distribution main work on Roslyn Road between Westbury Avenue and East 2nd Street. The outreach team will continue to keep residents informed during work and give notice of upcoming activities, maintaining social distancing and eliminating any close contact.

*Over the next week, neighbors can expect to see:

-Trenching on Roslyn Road between Jericho Turnpike and Raff Avenue.
-Gas main installation on Roslyn Road between Roselle Street and Jericho Turnpike.
-Backfilling and temporary restoration on Roslyn Road between Lee Avenue and Roselle Street.

Traffic Management Updates:

-The road will be closed on Roslyn Road between East Williston Avenue and Jericho Turnpike. We will have flaggers in place to control traffic when our crews are not working.
-The center lanes will be closed on Roslyn Road between Jericho Turnpike and Raff Avenue, with the outermost lanes remaining open to traffic
-There may be parking restrictions on Roslyn Road near ongoing and upcoming work.
-Our crews will have flaggers present to redirect traffic as necessary.

As always, feel free to reach out by emailing us at NWNassau@NationalGridGasProjectsNY.com, or by calling our project outreach team at (516) 882-4864. You can also use the Contact Us page of our website to submit any questions, comments, or concerns.