Happy New Year! Our construction team will be returning from the holiday break this week and will begin work in Garden City. We will be resuming daytime work hours for the duration of this phase of construction. The outreach team will continue to keep residents and businesses informed during work and give notice of upcoming activities, maintaining social distancing and eliminating any close contact.
*Over the next week, neighbors can expect to see the following activities during work hours:
- Gas main installation, backfilling and temporary restoration on County Seat Drive between South Drive and 11th Street.
- Trenching on 11th Street between County Seat Drive and Kellum Place
Traffic Management Updates:
- There will be changes in the traffic pattern on County Seat Drive and 11th Street during work hours.
- Our crews will have flaggers present to redirect traffic as necessary.
As always, feel free to reach out by emailing us at NWNassau@