s Updates Archive - National Grid: Nassau

Updates

Here you’ll find the latest information regarding the Northwest Nassau Natural Gas Integrity Project. Make sure to use the Contact Us page and sign up to get these updates directly to your email inbox.

Thank you for continuing to follow the progress on the Northwest Nassau Integrity Project. We are pleased to note that we are beginning work on the next phase of the project this week. This phase will entail the installation of…

Read More

We plan to resume construction on the Northwest Nassau Natural Gas Reliability Project in April 2023. We look forward to resuming our community outreach program prior to the beginning of construction activities. You can expect to receive notifications from our…

Read More

Last week, our construction team continued work on the concrete road base on Kellum Place between 9th Street and Stewart Avenue and continued road restoration on the Westbound LIE Service Road and Roslyn Road. *Over the next week, neighbors can expect…

Read More

Last week, our construction team continued work on the concrete road base on Kellum Place, backfilling the section between 10th Street and 11th Street and continuing excavation and casting of the road base between 9th Street and Stewart Avenue. *Over the…

Read More

Last week, our construction team continued work on the concrete road base on Kellum Place. *Over the next week, neighbors can expect to see the following activities during work hours: Continued work on the concrete road base on Kellum Place in…

Read More

Last week, our construction team continued work on the concrete road base on Kellum Place. *Over the next week, neighbors can expect to see the following activities during work hours: Continued work on the concrete road base on Kellum Place…

Read More

Last week, our construction team began work on the concrete road base on Kellum Place. *Over the next week, neighbors can expect to see the following activities during work hours: Continued work on the concrete road base on Kellum Place…

Read More

Last week, our construction team continued commissioning activities and backfill on the LIE Westbound Service Road near Locust Lane and Old Brick Road. *Over the next week, neighbors can expect to see the following activities during work hours: Backfilling and…

Read More

Last week, our construction team continued commissioning activities on the LIE Westbound Service Road near Old Brick Road and completed temporary restoration on County Seat Drive, on Roslyn Road north of Westbury Avenue and on Roslyn Road north of East Williston…

Read More

Last week our construction team continued commissioning activities on the LIE Westbound Service Road near Locust Lane and near Old Brick Road and on Coolidge Avenue in Roslyn Heights. *Over the next week, neighbors can expect to see the following activities…

Read More

Dear Neighbor, Last week, our construction team continued commissioning activities on the LIE Westbound Service Road near Locust Lane and near Old Brick Road, and on Roslyn Road in East Williston. *Over the next week, neighbors can expect to see…

Read More

Last week, our construction team continued work on the LIE Westbound Service Road near Locust Lane and near Old Brick Road, and continued commissioning activities in Mineola. *Over the next week, neighbors can expect to see the following activities during work…

Read More

Enter your email below to receive the most recent construction updates direct to your inbox! You can also call or email your local project team with any questions, concerns, or suggestions.